Previous Year Question Paper

Product and Material Management (MBA IV SEM)-Summer 2015

Short Question (2 Marks)

Question No. 1:-
(A) Define the Term Supply Chain Matrix ?
(B) What is meant by Sales and Operations Planning ?
(C) State the role of follow up Function in Production Planning ?
(D) Enlist the Establishing Specification of Purchasing ?
(E) What is meant by Periodic Review System ?
(F) Mention the Elements of Capacity Planning ?
(G) Define the Term Safety Stock
(H) Name the Factors to Design Requirement Planning ?
(I) Enumerate the term Capacity Planning ?
(J) Enlish the Factors of Order Point System ?
(K) What is Meant by Price Determination ?
(L) State the basic Element of JIT ?
(M) Mention the merits and demerits of JIT ?
(N) Enlist the Methods of Selecting Suppliers ?

Long Question (10 Marks)

Que No. 2:- Explain Production Planning and discuss developing of MPS in details ?

Que No. 3:- Describe the Concept of Enterprise Resource Planning i details and enumerate the making of effective production plan with suitable example?

Que No. 4:-Enumerate the term Economic Order Quantity and discuss its variations in details?

Que No. 5:-How to determine service level ? Also explain Periodic Review System in details ?

Que No. 6:-Discuss the Function of Purchase department in industry and also explain some methods commonly adopted in Industrial Purchasing ?

Que No. 7:- What do you understand by KanBan? Explain the Concept of Kanban System in Details?

Que No. 8:- Discuss impact of Material Requirement planning on purchasing and enumerate about supplier Selection ?

Que No. 9:- Explain the concept of JIT. How does it help the Manufacturing system to Improve Productivity ?



Que No. 10:- Enumerate the concept Lean Production in details and differentiate between Kanban and JIT.


Project Management (MBA IV SEM)-Summer 2015


Short Question (2 Marks)

Question No. 1:-
(A) What do you mean by Project Management ?
(B) Elaborate the concept of Knowledge Management ?
(C) How does Knowledge Management fit into a Project Management context ?
(D) Enlist the advantages of Resource Co-ordination ?
(E) What is Process Mapping ?
(F) What is critical chain ?
(G) WHat are different types of Cost involved in Project Management ?
(H) Define Critical Path ?
(I) Write objective of Project Planning ?
(J) What are the merits of Project Scheduling ?
(K) What do you mean by Quality Conformance ?
(L) What are the major elements in Managing Project Risk ?
(M) How is Critical Path useful ?
(N) Elaborate the concept of Matrix Management ?
(O) What are the advantages of Effective Team Work ?

Long Question (10 Marks)

Que No.2:- What are all roles you will need on a Project Management Team ?

Que No.3:- Discuss the Project Management Process ?

Que No.4:- How general Management and Project Management is related ?

Que No.5:- Discuss Project Management as a Strategic Capability ?

Que No.6:- Explain Quality Planning Process ?

Que No.7:- Discuss the steps to manage the risk effectively in an Organization /

Que No.8:- Elaborate the components of Project Quality Plan ?

Que No.9:- Describe work breakdown structure with the help of Diagram and Example /

Que No.10:-A small project is composed of 7 activities whose time estimate are listed in table below.Activity estimated duration n weeks:-

Activity
Optimistic
Most Likely
Pessimistic
1-2
1
1
7
1-3
1
4
7
1-4
2
2
8
2-5
1
1
1
3-5
2
5
14
4-6
2
5
8
50-6
3
6
15

Estimate:-
(a) Draw the Project Network and identify all Paths through it.
(b) Final expected duration.